VICTORIAN BUILDING PERMITS

Small second dwellings.
The 80 m² rule.

A larger second dwelling may now fit on your block. Start by checking how the floor area is measured, where the building can sit and which permits your property needs.

Reviewed .

01

Measure from the outside of the walls

Under the amended building definition, a small second dwelling is a Class 1a building on a lot that already contains exactly one Class 1 building. Its gross floor area may be up to and including 80 m². Measure to the outside face of external walls, or the centreline of a shared wall.

Show attached or abutting structures such as a deck, verandah, patio or pergola separately on the plan. The regulation excludes their area from the 80 m² calculation. For example, a 78 m² dwelling and a qualifying 10 m² attached deck can meet the floor-area test. The deck still needs to be shown for the site assessment.

02

Check the planning scheme for the address

Planning Amendment VC306 changed the planning definition on 15 October 2026. A building permit is required. Many sites can proceed without a planning permit, but the zone, lot size, overlays and site conditions can trigger one. Check with the council before finalising the layout. The dwelling cannot be subdivided from the main home under the small second dwelling provisions.

03

Show setbacks, windows and neighbouring solar panels

On the site plan, mark boundaries, building heights, ground levels, neighbours’ habitable-room windows and private open space. Identify existing rooftop solar panels on adjoining properties. The Part 5 changes address side and rear setbacks, daylight, overlooking, open space and solar access. Which controls apply depends on your planning and building permit pathway.

Where a Part 5 departure requires council report and consent, identify the regulation, show the departure on the plans and address the relevant decision guidelines in the current MG-12. Page 1 still prints the former 60 m² wording. The amendment on Gazette page 9 sets the 80 m² limit. A neighbour’s comment is one piece of evidence in that process.

04

Bring any earlier permit or dated design work

The building amendments commenced on 27 October 2026. If a building permit was already issued, or design work was substantially progressed, give the surveyor the permit and dated drawings. Section 10 can preserve the earlier building rules for work under an existing permit or where the relevant building surveyor certifies substantial design progress in writing. The owner and surveyor may agree to use the new rules. Any planning transition must be assessed separately.

Send the address, proposed floor-area calculation, site plan, any planning permit and endorsed plans with your enquiry. We can then identify which building approval documents you need.

Victorian building permit services

Prepare your Victorian application

LET’S TALK ABOUT YOUR PROJECT

Discuss your
building project.

Discuss your project